Show "sliding ToDos" in Calendar

Here we post and discuss the iCal calendars which users create with EssentialPIM
Post Reply
gm2904
Posts: 4
Joined: Wed Dec 08, 2010 2:48 pm

Show "sliding ToDos" in Calendar

Post by gm2904 »

As a 10 years long user of Lotus Organizer 6, I am used to "sliding tasks" showing in calendar section. By that I mean that a task with a given completion date will keep showing in Calendar on ToDay when overdue, as long as it is not declared 100% completed. Is it possible to obtain the same behavior for overdue tasks in ePIM ???
Max
Site Admin
Posts: 21714
Joined: Wed Dec 08, 2004 11:39 pm
Has thanked: 819 times
Been thanked: 364 times
Contact:

Re: Show "sliding ToDos" in Calendar

Post by Max »

Thanks, suggestion noted. So far not many requests for this, so I can not promise quick implementation.
Maxim,
EPIM Team
User avatar
Your V Gal
Experienced
Posts: 41
Joined: Sat Jul 07, 2012 4:31 am
Has thanked: 3 times
Been thanked: 2 times

Re: Show "sliding ToDos" in Calendar

Post by Your V Gal »

I would LOVE this idea as I waste too much time moving 'top projects' from one day to another if I don't get them done. The only way they stay on my priority list is on the Daily Calendar. I also would love a way to 'bulk' move tasks from 1 day to the next rather than one by one.
admin
Site Admin
Posts: 15601
Joined: Thu Nov 25, 2004 3:12 am
Has thanked: 1411 times
Been thanked: 984 times

Re: Show "sliding ToDos" in Calendar

Post by admin »

The first suggestion is in the plans. As for the second one about bulk moving of tasks - this feature became available in EPIM 9.6.
Android version of EssentialPIM. Keep all your data in sync!
locke
Guru
Posts: 399
Joined: Thu May 20, 2010 10:58 am
Has thanked: 14 times
Been thanked: 29 times

Re: Show "sliding ToDos" in Calendar

Post by locke »

I know the solution of floating dates in other Apps. These will always be postponed by one day if they are not done.