hi, :)

i have a task-series for my university-lectures. i repeated it for every week on the same day. then i deleted the ones which were on holidays (e.g. easter, ...) etc.

since i didn't know the location where this lectures will take place, i left this field empty.

now, that i know where they take place, i edited the series, entered the "location", and pressed "OK". epim now "reentered" all my deleted occurences of the lectures. so i have to recheck with every lecture, each week, whether it takes take place or not... i think if you edit a series, it should only update the current tasks, unless i change the repeat-values...

thx
bye
chris

PS. Version Essentialpim Pro 3:23, Windows 7 32Bit
veganchris
Novice
Posts: 21
Joined: Wed May 02, 2007 8:30 am

Re: edit task-series problem

Post by veganchris »

is this really a problem to update only the current occurences of the tasks-series, instead of creating new ones again? you could e.g. ask the user beforehand like "update only current occurences - yes/no"...
Max
Site Admin
Posts: 21714
Joined: Wed Dec 08, 2004 11:39 pm
Has thanked: 819 times
Been thanked: 364 times
Contact:

Re: edit task-series problem

Post by Max »

Thank you. I agree, that looks like a bug. We will try to fix it, but probably after 3.5 version.